Stanford Avenue/El Camino Real Intersection Improvement Project



CONSTRUCTION UPDATE

Project Timeline:  Late February 2011 to October 2011

NOTICE OF UPCOMING WORK: 

Stage 5 (MEDIAN): Contractor will begin work for the widening of the median. Left turn lanes will be impacted/closed. SOUTHBOUND El Camino Real traffic turning left onto eastbound Stanford Ave will be closed thru September 19, 2011.  Please follow detour signs.  NORTHBOUND El Camino Real traffic will be able to turn left onto Westbound Stanford Avenue until 10 am and after 5 pm daily, beginning the week of August 22.

 

 

Week of August 15 – 19:

Contractor will begin sawcut & demolition of the medians. Contractor will be installing irrigation required for landscaping.

 

Signal poles will be installed on Stage 4 (Northwest corner).

 

Week of August 22 – 26:

Contractor will continue to work on the median. Contractor will begin grading and forming the curbs for the widened median.

Left turn lane from Northbound El Camino Real onto Westbound Stanford Avenue will be open until 10 am daily.  Detours will also be in place.

 

This project includes the installation of new landscaped corner bulbouts, realignment and enhanced/textured paving of pedestrian crosswalks, new pedestrian refuges, widened landscaped medians, street furniture, new ornamental sidewalk lights and replacement of traffic signal poles. Of particular importance at this intersection will be the enhanced crosswalks, median refuges and reduced crossing distances for pedestrians and bicyclists.

The City’s contractor Pavex Construction Co. will be starting construction on the Stanford Ave and El Camino Real Intersection Improvements project mid February 2011 with the installation of project construction signs.  Actual construction is scheduled to start late February/early March 2011 with the shifting of the lane striping to allow for protected construction areas at all 4 corners of the intersection. 

Pedestrian and bike access through the project will be maintained at all times.  Please be aware that directional and informational signs will be in place to direct pedestrian flow of travel around the ongoing construction work.

If you have any questions or comments, please contact the City of Palo Alto onsite Construction Manager, James Beauchamp at (650) 302-1402 or by email at :  james@ghirardelliassoc.com  



Related Materials:

Conceptual Plan

Project Plan I
Project Plan II

Planning & Transportation Commission Report January 13, 2010
Architectural Review Board Report January 7, 2010

For general questions on this project, plese contact the Transportation Divison at (650) 329-2520 or  Email:  transportation@cityofpaloalto.org

Last Updated: November 10, 2009