Water Main Replacement Project

Purpose: Replace cast iron and other aging pipelines with high density polyethylene mains.

Scope: The work to be performed under the contract includes installation of approximately 12,626 linear feet of new water mains of various sizes, 163 new water services, and 30 new fire hydrants. The new main sizes range from 8” to 12” in diameter. The new mains will be installed by horizontal directional drilling and open trench methods.

Please review this map for the specific project locations.

Project Manager (City): Robert Item, (650) 566-4513 
Engineer (City):
Marina Ezrina, (650) 566-4519
Contractor:
Daleo, Inc. 
Field Inspector (City):
Steve Richey, (925) 413-9310

24-hours Utilities Water-Gas-Wastewater Emergencies: Dispatch, (650) 329-2413 or (650) 329-2579

Project Schedule:
The project duration is approximately 11 months, or 218 working days.  Construction is scheduled to start in June 2017. Weather delays may impact duration of construction.

Working Hours: Work typically will be performed Monday through Friday 8:00 a.m. to 5:00 p.m.

There are restricted work hours applied to major streets and streets within certain proximity of schools.

Project Progress Update:

8/8/2018

Area I – Hamilton Avenue
Complete
Area II – Everett Avenue
Complete
Area III – Hawthorne Avenue
Complete
Area IV – Oregon Avenue between High and Waverley
Near completion.
Area V – Waverley Street between Churchill and Lowell Avenues (addition to project scope) 
Construction has started on July 16, 2018 and will continue until mid-September 2018.

5/30/2018

 Area I – Hamilton Avenue
Complete
Area II – Everett Avenue
Complete
Area III – Hawthorne Avenue
Contractor has been working  on Hawthorne Avenue. Completion is anticipated by the end of June 2018. 
Area IV – Oregon Avenue
Construction has started on May 30, 2018 and will continue until end of July 2018.
Area V – Waverley Street between Churchill and Lowell Avenues (addition to project scope) 
Work is anticipated to begin in July 2018 and will continue until mid-October 2018.

3/30/2018
Area I – Hamilton Avenue
Complete
Area II – Everett Avenue
Completed, except for final pavement restoration at various locations between Bryant and Middlefield. 
Area III – Hawthorne Avenue
Contractor has been working  on Hawthorne Avenue. Completion is anticipated by mid-May 2018. 
Area IV – Oregon Avenue
Work will begin in the middle of May 2018 and will continue until end of July 2018.

11/16/2017 :  
Area I – Hamilton Avenue
Contractor is expected to finish construction activities on Hamilton by November 22, 2017.  
Area II – Everett Avenue
Contractor has been working  on Everett Avenue. Completion is anticipated by March 2018. 
Area III – Hawthorne Avenue
Work will begin at the end of January 2018 and will continue until June 2018.

10/24/17: Work has begun on Hamilton Avenue.  Contractors are expected to finish construction activities in that area by November 22, 2017.  Work on Everett Avenue has begun and will continue until February of 2018. 

Contract Amount: $4,987,424.35