Project: Sanitary Sewer Rehabilitation Project 28B (SSR 28B)

 Contract No. C19174627

Contractor:  Ranger Pipelines, Inc. 

Amount:  $1,930,066

Description:  Replacement of approximately 7,655 feet of sewer pipes, 77 service laterals, and 12 manholes.

Map of Entire Construction Area

Utility Project Manager: Romel Antonio (650) 566-4518

Utility Project Engineer:  Eli Mejia (650) 566-4572

Utility Field Inspector:  Andre Rodriguez (650) 740-2451

After Hours: (650) 329-2413

Construction Start Date:  August 2019

Construction End Date:  October 2019