This project will rebuild and replace the underground electric system in Underground District 26. Work will include the replacement of deteriorated electrical cables, transformers, switches, and enclosures. Installation of new equipment will bring the electrical system up to current construction standards.
This project is currently in the planning stage. Estimated project to begin in Spring 2021.
Spring 2021
Reconfigure circuit on Arastradero Rd north of Deer Creek Rd and south of Foothill expressway. Remove old equipment and install new equipment.
Spring 2022
Complete rebuild along Arastradero Rd between Foothill Expressway and Ynigo Way. Removing old equipment and installing new equipment.
Spring 2023
Complete rebuild between Ynigo Way and Los Palos Ave. Removing old equipment and installing new equipment.
Spring 2024
Complete rebuild between Los Palos Ave. and Irven Ct. Removing old equipment and installing new equipment.
UGDT 26 Boundary Map(PDF, 272KB)
Electric Engineering Department
General Inquiry: (650) 566-4500
Contact: Greg McKernan
Phone: (650) 566-4575
Email: Gregory.McKernan@cityofpaloalto.org
TBD
Last updated on April 07, 2021