Gas Main Replacement 23

  • Project typeGas Main Replacement
  • Project value$6,417,876.05

Project Description

The Natural Gas Main Replacement Project 23 replaced approximately 22,300 linear feet of polyethylene (PE) gas main, 142 new PE gas service pipelines, and to reconnect 64 existing PE gas services to the new gas main within the City of Palo Alto. The Project targeted replacement of Polyvinyl Chloride (PVC) gas mains and gas services that were nearing their operational life expectancy and had become brittle over time. The project also targeted replacement of steel mains and services that were identified to be severely corroded due to the lack of cathodic protection.

Scope of Work

Replaced the gas distribution system with PE

  • Installed PE gas main and new gas services. 
  • Reconnected existing PE gas service to the new PE gas main. 

Project Status 

Gas Main Replacement Project 23 was completed in July 2022.

Location

GMR 23 Project Map(PDF, 1MB)