Stage 3 – 2019 to 2020

Status: Completed

Date(s):

  • January 2019: California Avenue Area Parking Garage construction begins
  • July 2019: Public Safety Building Design approved by the Architectural Review Board with items for subcommittee review
  • July 2019: Architectural Review Board Subcommittee Meeting for the Public Safety Building
  • December 2019: Architectural Review Board Subcommittee Meeting for the Public Safety Building
  • February 2020: City conducts contractor pre-qualification for the Public Safety Building
  • June 2020: City conducts a second contractor pre-qualification for the Public Safety Building
  • September 2020: The Public Safety Building project goes out to bid to the pre-qualified contractors.
  • December 2020:  Bids received in November were rejected. The Public Safety Building project is re-bid to the pre-qualified contractors.
  • The California Avenue Area Parking Garage opens to the public on December 8, 2020.