Charleston / Arastradero Corridor Project

  • Project typeTraffic and Transportation
  • Project value$19,554,473
  • Completion DateMay 09, 2023

Project Description

The 2.3 mile Charleston-Arastradero Corridor is a heavily used, residential-arterial road that serves as an east-west connector for the southern section of Palo Alto. The corridor connects eleven K-12 schools, several parks, shopping centers, community centers, senior living facilities, and a library. The project includes installing landscaped medians, curb extensions/bulb-outs, enhanced bicycle and pedestrian improvements, and traffic signal modifications consistent with the existing striping/roadway configuration.

Arastradero and Charleston Roads were paved with Rubberized Hot Mix Asphalt (RHMA), which uses ground tire rubber blended with asphalt binder and aggregate materials. The California Department of Resources Recycling and Recovery (CalRecycle) provided funding for the paving work under the Rubberized Pavement Grant Program. A total of 10,115 tires were diverted from the waste stream.

Scope of Work

  • Enhanced safety for K-12 students walking and biking to school and other corridor users.
  • Smoother traffic flow along the corridor.
  • Streetscape beautification: the project will add approximately 80 trees, shrubs, groundcover, grasses, and bioretention plants throughout the 37,000 square feet of landscaped elements.

Scope of Work (expanded)

The overall objective of the project is to address the needs of nearby residents and the surrounding community who have requested an improved corridor with more moderate vehicle speeds, safer conditions, and various vegetation improvements will be used to enhance the aesthetic quality of the corridor and treat stormwater.

Landscaped medians will improve safety for pedestrians, bicyclists, and other motorists from users making abrupt lane changes and dangerous turns. Pavement markings will help a driver’s awareness of pedestrians and bicyclists. To further protect bicyclists, the corridor will have a dedicated or buffered bike lane. More details on the streetscape improvements included in the project can be in the project FAQs(PDF, 2MB).

Another key component of the Charleston-Arastradero Corridor Project is the upgrade of traffic signal equipment for increased controllability of signals. An adaptive traffic control system will also be implemented as a part of this project. It will optimize signal timings which will improve traffic flows. In addition to traffic signal modifications, a new traffic signal will be installed at Louis/Montrose and E. Charleston Road.

The Charleston-Arastradero project has been in the works for almost 15 years with significant stakeholder outreach and community engagement. The City Council approved the concepts for the corridor in 2015, and the Architectural Review Board approved the landscape plans in 2017. Federal grants fund part of the project, which requires a phased construction approach. Phase 1 includes the corridor section Arastradero Road between Foothill Expressway to Clemo Avenue. Phase 2 includes corridor section of West Charleston Road from Alma Street to Middlefield Road. Phase 3 of construction will be the remaining sections of the corridor between Los Palos Avenue to Alma Street and Middlefield Road to San Antonio Road. 

Project Status  

Upcoming Work 

Middlefield Road Traffic Signal Cable Work
In continuation from the Middlefield switchover, the contractor will be working within the traffic signal cabinet at the intersection of Middlefield Road and E Charleston Road for cable work on March 30. Traffic delays are expected during construction hours from 9 a.m. to 4 p.m. 

Concrete Work at El Camino Real 
The contractor will be removing and replacing concrete sidewalks, curb ramps, curbs, and gutters starting at the southern intersection corners of El Camino Real and W Charleston/ Arastradero Road. Work is currently scheduled to start on March 30, weather permitting, and is estimated to be complete by the end of April.

Traffic Signage Installation
The contractor will resume installing a new traffic signal on Arastradero and Charleston roads the week of March 27, weather permitting. Work is estimated to take a couple of weeks to complete.

Concrete Patching Work
The contractor will be doing concrete patching at various locations throughout the corridor, where temporary asphalt was placed due to removing old signal pole foundations and irrigation crossing work. The contractor will be pouring concrete back at these locations following the completion of the El Camino Real concrete work. Work is estimated to start the week of April 24 and take a week to complete.

El Camino Real Landscape Planting
Following the completion of the concrete work, the contractor will be installing landscaping at the northeast and southeast intersection corners of El Camino Real and W Charleston/ Arastradero Road. Work is estimated to start at the end of April and take a week to complete.

Remaining Project Activities

Although the project is making steady progress, there are several outstanding construction activities that need to take place before completion, including:

  • Improvements at the El Camino intersection, which includes paving and striping. 
  • Signal activation at the Wilkie Way intersection.

The City will communicate schedule updates as dates for these activities get finalized -- pending the delivery of traffic signal equipment and coordination with other agencies.

Project Timeline

  • Phase 1

    06/2018 - 11/2020

    Roadway improvements have been constructed on Arastradero Road from Foothill Expressway to Clemo Avenue.  Improvements included are curb extensions, sidewalk expansions, enhanced bicycle lanes, a protected cycle track, traffic signal improvements, landscaped median islands, new lane configurations, and new street trees. Phase 1 was completed in November 2020.

  • Phase 2

    06/2018 - 11/2020

    Roadway improvements have been constructed on E. Charleston Road from Alma Street to Middlefield Road. Improvements included are curb extensions, sidewalk expansions, enhanced bicycle lanes, traffic signal improvements, landscaped median islands, new lane configurations, and new street trees. Phase 2 was completed in November 2020.

  • Phase 3

    Roadway improvements are planned in the remaining segments of the Charleston-Arastradero Corridor on Arastradero Road from Los Palos Avenue to El Camino Real, W. Charleston Road from El Camino Real to Alma Street, and E. Charleston Road from Middlefield Road to San Antonio Road. Similar improvements from Phase 1 and Phase 2 will be implemented in Phase 3 such as curb extensions, enhanced bicycle lanes, landscaped median islands, traffic signal improvements, new lane configurations, and new street trees.

Upcoming Meetings

There are no scheduled meetings at this time.

Past Community Meetings

September 9, 2021 – Phase 3 Informational Meeting
The public was invited to learn more about the project and what to expect to see during construction. Staff and the consultant team were available to answer questions. The presentation slides from this meeting are here.(PDF, 42MB)

 

June 22, 2021 – Council Meeting
City Council reviewed staff’s recommendation to approve the construction contract with O’Grady Paving for Phase 3 of the Charleston-Arastradero Corridor Project.

November 20, 2019 – Walkthrough at Los Altos – Hetch-Hetchy Bike Path
Approximately 40 community members attended the meeting and site walkthrough on Wednesday, November 20 to review the scope of the upcoming tree work. City staff explained the tree removals and maintenance work, described the City’s efforts to minimize the impacts to the trees, and answered questions from attendees. The work is described in the meeting’s handout.(PDF, 2MB)  

October 9, 2019 - Walkthrough at Los Altos – Hetch-Hetchy Bike Path
The City held a walk-through meeting at the SFPUC Los Altos-Hetch Hetchy bike path to discuss tree pruning along the path and why it is required.

May 21, 2018 – Council Meeting
City Council reviewed staff's recommendation(PDF, 3MB) to approve construction contracts with O'Grady Paving for Phase 1 and 2 of the Charleston / Arastradero Road Corridor Project. 

March 27, 2018 – Open House at Gunn High School
The public was invited to learn more about the project and staff were available to answer questions. 

March 29, 2018 – Open House at Hoover Elementary
The public was invited to learn more about the project and staff were available to answer questions 