Stage 2 – 2017 to 2018

Status: Completed

Date(s):

  • Design of the California Avenue Area Parking Garage begins.
  • Draft EIR of the Public Safety Building and California Avenue Area Parking Garage begins.
  • October 2017: Architectural Review Board Meeting for the Public Safety Building and California Avenue Area Parking Garage projects
  • January 2018: Final Draft Environmental Impact Report completed.
  • January 2018: Architectural Review Board Meeting for the California Avenue Area Parking Garage 
  • March 2018: Architectural Review Board approves the California Avenue Area Parking Garage project
  • June 2018: Final Environmental Impact Report – Notice of Determination
  • Construction Documents are completed in Fall 2018
  • California Avenue Area Parking Garage project goes out to bid in September 2018
  • December 2018: Council approved and authorized a construction contract for the New California Avenue Area Parking Garage