College Terrace Traffic Calming Project

Council approved a one-year trial traffic calming plan for the College Terrace neighborhood.

Project Overview
The College Terrace neighborhood is bounded by El Camino Real on the east, California Avenue on the South, Amherst on the west and Stanford Avenue on the north.

In November 2004, the Palo Alto City Council approved a one-year trial traffic calming plan for the College Terrace neighborhood. The plan was developed by the Transportation Division in consultation with the residents, based on a study of speeds, volume and cut-through traffic on perimeter and interior streets.

Trial Plan
The physical traffic calming devices approved by the City Council includes six speed tables designed to gently slow vehicles exceeding the speed limit on the perimeter of the neighborhood and five traffic circles to improve safety at intersections interior to the neighborhood which experience the most cut-through traffic. On October 26th, 2006 a letter was sent to all the residents notifying them of start of construction.

The locations for these devices are as follows:

  • Stanford Avenue: Four speed tables, located just west of the intersections with Wellesley Street, Oberlin Street, Dartmouth Street and Amherst Street
  • California Avenue: Two speed tables, located just west of Wellesley Street and just east of Oberlin Street
  • College Avenue: Four traffic circles, located at the intersections of College Avenue with Yale Street, Oberlin Street, Hanover Street and Columbia Street
  • Cambridge Avenue: A small traffic circle at the intersection of Cambridge Avenue with Yale Street

During the trial period, effectiveness of the physical traffic calming measures, level of community acceptance as well as any potential impacts will be monitored. Performance measures related to safety, speed, and volumes will be used to evaluate the trial.

College Terrace Traffic Calming Project
College Terrace Traffic Calming Project Notice of Start of Construction
On October 26th, 2006 a letter was sent to all the residents notifying them of start of construction of physical traffic calming devices .
Revision Date: 06/20/2007
Picture of Existing Traffic Circles
Revision Date: 06/20/2007
Pictures of Existing Speed Tables
Revision Date: 06/20/2007
Project update
On August 13, 2008 a letter was sent to all the residents notifying them of the evaluation of the traffic calming measures.
Revision Date: 08/18/2008
Speed Tables And Raised Crosswalks
Revision Date: 06/20/2007
Traffic Circles
Revision Date: 06/20/2007
Resources
Approved College Terrace Trial Plan Map
Revision Date: 06/20/2007
Planning and Transportation Commission Staff Report (September 8, 2004)
Trial Implementation of College Terrace Traffic Calming Plan and Attachments A-I
Revision Date: 06/20/2007
Recommended Trial Implementation of the Selected Traffic Calming Plan in the College Terrace Area-(November 22, 2004)
Revision Date: 06/20/2007