A two-year trial of the Corridor Project began in Summer 2006.
Phase One Improvement Schedule
- Site preparation at Gunn High School - May 2006
- Dedicated right turn lane construction and intersection improvements at Gunn High School - Late June – Late August 2006
- Pavement striping and resurfacing from Fabian Way to El Camino Real - July 2006
- Traffic signalization improvements - July 2006
- Monitor and evaluate Phase One - September 2006 – June 2007
Stay Informed
A project infoline and a website have been established for community members to join the mailing list, receive updated information, ask questions and provide comments. in addition, periodic email updates and community meetings are planned to keep the community informed during construction.