City of Palo Alto Homepage
TEXT VERSION 
SEARCH FOR:
Typical Gas Project Construction Stages

 

Typical construction durations shown are approximate. Actual duration may vary dependent on existing conditions, site-specific road/traffic conditions, and weather conditions.

 

For updated current information on when construction will occur in your specific area, please contact the Project Engineer, City of Palo Alto, Water-Gas-Wastewater Engineering.

 

FAQs for Construction of Capital Improvement Projects

 

 

Gas Project Stages

CONSTRUCTION PHASE

DESCRIPTION

TYPICAL DURATION

 

Site Mobilization

 

Contractor moves equipment and material near the construction area or to their storage yard. Contractor marks the boundaries of the area for underground Service Alert (USA).

1 - 2 working days

USA / Survey

Underground Service Alert (USA) and City Survey Crew marks out existing utilities and proposed gas main alignment on the street pavement with spray paint.

2 - 5 working days

Sawcutting

The Contractor sawcuts existing pavement as marked by the survey crew.

1 - 3 working days

Excavation

The Contractor removes pavement and excavates soil to prepare for installation of a new gas main and services.

1-3 working days

New Gas Main, Services Installation, and Existing Services Reconnection

The Contractor installs the new polyethylene gas main by directional boring methods and either installs new or reconnects existing services.

2-6 working days

 

New gas main and service air pressure test

 

The Contractor performs air pressure tests on the new gas main and services before connecting them.

The gas main and services are pressurized with air at 100 PSIG for 24 hours.

For a typical city block: 2 - 5 working days.

Backfilling

Contractor fills and compacts the ground openings with backfill material as the new main is installed.

Performed concurrently with the new main and services installation and connection

Install Temporary Pavement or "Cutback"

Temporary cold asphalt mix is placed on the backfilled area to temporarily restore the roadway service. If your street is concrete, steel plates will be placed on top of the trench in order for the concrete base to cure, prior to final restoration.

Performed concurrently with the new main and service installation, connection, and backfill

Purging the new gas main and services and tie-in into the system

The City crews purge air from the new main and services and connect the main into the existing gas system.

3-5 days per block

 

Final Pavement Restoration

The Contractor removes temporary asphalt pavement, steel plates, and restores pavement and all surface improvements to the preconstruction condition

1-3 days per block

 

Modification of house gas plumbing systems

 If gas meter has been relocated, the Contractor modifies and tests the customer’s house gas plumbing system.

4 hours to 1 working day

 

Surface restoration

 The Contractor restores all existing improvements and landscaping at each location to the preconstruction condition.

After completing the plumbing work at each house location

Service Transfer

The City crews transfers each building’s individual gas supply from the old to the new gas system.

Gas service interruption due to transfer should not exceed 8 hours.

Pilot Relighting

The City customer service representatives relight pilots at each house that was transferred from the old to the new gas systems.

Before 5 p.m. on the day of the service interruption or after hours upon contact from customer. Please call (650) 329-2413 or (650) 329-2579.

Final cleaning

The Contractor sweeps the street affected by the project and removes USA markings.

1-2 days per block

 




Acceptable Use PolicyAccessibilityYour PrivacySite MapSearch EngineA-Z IndexComment FormMissing Content

 
City of Palo Alto City Hall - 250 Hamilton Ave, Palo Alto, CA 94301 | Main Telephone Number 650-329-2100 8am-5pm M-Th, Alt Fridays