City of Palo Alto Homepage
TEXT VERSION 
SEARCH FOR:
Typical Water Project Construction Stages

Typical construction durations shown are approximate. Actual duration may vary dependent on existing conditions, site-specific road/traffic conditions, and weather conditions.

 

For updated current information on when construction will occur in your specific area, please contact the Project Engineer, City of Palo Alto, Water-Gas-Wastewater Engineering.

 

FAQs for Construction of Major Capital Improvement Projects

 

Water Project Stages

CONSTRUCTION PHASE

DESCRIPTION

TYPICAL DURATION

Site Mobilization

Contractor moves equipment and material near the construction area or to their storage yard. Contractor marks the boundaries of the area for underground Service Alert (USA).

1 - 2 working days

USA / Survey

Underground Service Alert (USA) and City Survey Crew marks out existing utilities and proposed water main alignment on the street pavement with spray paint.

2 - 5 working days

Sawcutting

The Contractor sawcuts existing pavement as marked by the survey crew.

1 - 3 working days

Excavation

The Contractor removes pavement and excavates soil to prepare for installation of a new water main, fire hydrant laterals and services.

1-3 working days

New water main, services, fire hydrants, and existing services reconnection

The Contractor installs new water main by either directional boring method or open trench based on field conditions. Installs new services, fire hydrants, and reconnect existing water services.

2-6 working days

  New water system pressure and leak testing

The new water system undergoes a hydrostatic pressure test at 150 psi.

8 hours.

Fill new main with water for disinfection & Bacteriological Test

A liquid disinfectant is injected into the charged system to kill any pre-existing microbial organisms. Water is sampled and taken to a laboratory for analysis.

48 hours

Service Transfer Connections

Once the Bacteriological Test has passed and written passing results are submitted, the Contractor connects new water piping into the water distribution system.

0.5-3 hours per service (this entails an individual water service interruption)

Backfilling

Contractor fills and compacts the ground openings with backfill material as the new main is installed.

Performed concurrently with the new main and services installation and connection

 

Install Temporary Pavement or "Cutback"

 

 

Temporary cold asphalt mix is placed on the backfilled area to temporarily restore the roadway service. If your street is concrete, steel plates will be placed on top of the trench in order for the concrete base to cure, prior to final restoration.

Performed concurrently with the new main and service installation, connection, and backfill

 

Final Pavement Restoration

 

The Contractor removes temporary asphalt pavement, steel plates, and restores pavement and all surface improvements to the preconstruction condition

1-3 days per block

 

 Final cleaning

 

 The Contractor sweeps the street affected by the project and removes USA markings.

1-2 days per block




Acceptable Use PolicyAccessibilityYour PrivacySite MapSearch EngineA-Z IndexComment FormMissing Content

 
City of Palo Alto City Hall - 250 Hamilton Ave, Palo Alto, CA 94301 | Main Telephone Number 650-329-2100 8am-5pm M-Th, Alt Fridays