Project 21 & 22 - Water Main Replacement Capital Improvement Project WS-07003 & 0817

Project Location Map        Project Construction Street List   

Scope: The work to be performed under the contract includes installation of approximately 33,515 linear feet of new high density polyethylene (HDPE) water main, 51 new fire hydrants, 14 copper new customer services, and service stubs to reconnect 669 existing customer copper services and to reconnect 13 existing fire services within the city limits of Palo Alto.

Contract Amount: $5,227,975
Contractor:  Ranger, Pipeline, Inc.
Project Manager (Contractor):  Liam Finnegan, (415) 559-1325
Project Manager (City):  Aleksandr Pishchik, (650) 566-4521
Project Engineer (City):  Darija Borkovic, (650) 566-4507
Field Inspector (City):  Casey Crary, (650) 740-2496
After hours: CPA Communications, (650) 329-2413

Project Schedule:   September 2009 through July 2010. The project duration will be approximately 10 months or 300 calendar days. Weather delays may impact this schedule. For precise information regarding the work schedule on your street, please contact Project Engineer.

Working Hours: Work will be performed Monday through Friday 8:00 a.m. to 5:00 p.m.


Notice of Construction Letter

Typical Project Construction Stages

FAQ's for Construction of Major Utility Projects

 




Acceptable Use PolicyAccessibilityYour PrivacySite MapSearch EngineA-Z IndexComment FormMissing Content

 
City of Palo Alto City Hall - 250 Hamilton Ave, Palo Alto, CA 94301 | Main Telephone Number 650-329-2100 8am-5pm M-Th, Alt Fridays