Project GS-07002
Project Location Map Project Construction Street List
Scope: The work to be performed under the contract includes installation of approximately 36,242 linear feet of new polyethylene (PE) gas main, 555 new customer services, and service stubs to reconnect 107 existing customer PE services. In some cases, relocation of natural gas meters from their present locations to new locations will be required to comply with the safety requirements as specified by the City's Utilities Standards. The relocation of gas meters usually involves a modification of the customer's house gas plumbing system to accommodate a new gas meter location. Customers whose gas meters are to be relocated will receive an individual written notification at least two weeks in advance of work being performed. Please review the attached maps for the project locations.
Contract Amount: $3,859,795
Contractor: Lewis And Tibbits Inc.
Project Manager (Contractor): Tim Freitas, (408) 925-0220
Project Manager (City): Greg Scoby, (650) 566-4514
Project Engineer (City): Liza Sorin, (650) 566-4537
Field Inspector (City): Andre Rodriguez, (650) 740-2451
After hours: CPA Communications, (650) 329-2413
Project Schedule: January 5, 2009 through October 19, 2009. The project duration will be approximately 9 months. Weather delays may impact this schedule.
For precise information regarding work on your street, please contact Project Engineer.
Working Hours: Work will be performed Monday through Friday 8:00 a.m. to 5:00 p.m.